EEC’s all five Infrastructure projects are on schedule.
EEC’s all five Infrastructure projects are on schedule.
1)Three Airport Rail Link
Announced bidding invitation November 2,
Sell TOR November 12.
Start service operation in 2023.
2) Utapao International Airport
Announced bidding invitation November 5,
Sell TOR November 20.
Start service operation in 2023.
3) Aircraft Maintenance Center (MRO)
Announced bidding invitation November 5,
Sell TOR November 20.
Start service operation in 2022.
4)Maptaput ,Industrial Port Phase 3.
Announced bidding invitation November 5,
Sell TOR November 9.
Start service operation in 2025.
5) Lamchabang ,Industrial Port Phase 3.
Announced bidding invitation November 1,
Sell TOR November 5.
Start service operation in 2023.
All projects were scheduled to disclose the bidding winner and sign the contract within February 2019.